The Didipio FTAA-001 straddles a mountainous region between the provinces of Nueva Vizcaya and Quirino in Northern Luzon ~270km north of Manila. Approximately 30 gold-copper prospects are known within the FTAA which have had varying levels of exploration over past years.
Employment
The company abides by the rules and regulations of the Labour Code as well as those set by Government Regulatory Agencies in the Philippines. Preference is given to local community members for employment opportunities at the project.
Australian and New Zealand Macraes goldfield  operator OceanaGold said its Didipio gold and copper project in the Northern  Luzon of the Philippines is now estimated to cost US$220 million, US$35 million  more than the company announced in June 2011.
OceanaGold also said it has credit approvals  from a group of large multi-national banks for a three-year US$220 credit  facility, subject to final documentation.
The main reasons for the Didipio cost blow-out  are "associated with increases in engineering design and procurement  services, the Tailings Storage Facility (TSF) and infrastructure construction  and site support costs," OceanaGold said.
"Working capital requirements on start-up  are expected to be an additional US$27 million."
At June 30, the company had spent US$161  million on the project with a further US$24 million committed in contracts.  Cash on hand was US$73 million.
"The Didipio project is going extremely  well. We remain on track to achieve our goal set out in June last year to  commence commissioning," in the December quarter 2012, said managing  director Mick Wilkes.
"The increased capital cost for the  project is consistent with industry cost pressures today, particularly for  engineering design services," Wilkes said.
"We also made the very deliberate decision  to engage with high-quality contractors in the Philippines which cost more  money to ensure the project was built to a high standard and on time."
In June last year, Wilkes said Didipio had a  "very robust" capital payback of one to two years, based on the then  estimated capital costs of US$185 million.
Now Wilkes said construction at the Didipio  project is more than 70% complete and is fully financed.
"Recruitment for Didipio permanent  operations team and operations readiness plans are well advanced" with  about 60% of the required positions already filled, it said.
Gold bars on display - Source: Reuters
Key outstanding items are the delivery of seven  power generators and electrical switch rooms but all power equipment should be  at the site over the next four to six weeks.
"Mining of the Didipio orebody has  commenced on schedule this month in readiness for commissioning in the fourth  quarter and to build ore stockpiles for production in 2013."
The credit facility will provide additional  liquidity if necessary to repay the A$57.8 million of OceanaGold's convertible  bonds maturing December 2012, repay the A$110 million of convertible bonds  maturing December 2013 and provide US$50 million in working capital, Wilkes  said.
Securing the facility is "a vote of  confidence in OceanaGold and allows us to focus on successfully commissioning  Didipio and generating strong cash flows from our operations in 2013," he  said.
In June 2011, Wilkes said the December 2012  bonds would be repaid from cash flow.
OceanaGold shares, which are dual-listed on  both the ASX and NZX, are up 3 cents at $2.40. While that's up from the  year-low at $2.18 in May, the shares have been trending down from $5.20 in  December 2010.
TVNZ News


Anonymous or Google Comment
Facebook Comment